Early works for Brisbane Stadium have been under way at Victoria Park since June 2026, and the Queensland Government says they are due to finish by the middle of 2027, with construction of the stadium to start soon after.
Sources: Queensland Government statements of 1 June 2026, 17 July 2026 and 18 November 2026.
What is happening on site
The early works contractor, BMD, started its next phase in August 2026, which includes bulk earthworks, haul roads, fencing, stormwater drains, retaining walls and a logistics plaza, according to the Queensland Government. Parts of the park have been closed since 1 June, and the government says more closures will be needed as construction goes on.
What it will be
The stadium will host the opening and closing ceremonies and athletics at the 2032 Games, then become Brisbane’s main stadium and the home ground of the Brisbane Lions, the Queensland Bulls and the Brisbane Heat. It is being designed by COX Architecture and Hassell with Japan’s Azusa Sekkei, according to the Queensland Government.
Quick answers
Has the stadium started?
Early works started in June 2026, and the Queensland Government says construction of the stadium will start after they finish in mid-2027.
When did the earthworks start?
Preparatory earthworks started in June 2026, and bulk earthworks started in August 2026.
Who is designing it?
COX Architecture and Hassell, with Azusa Sekkei, are designing the stadium, and GIICA is delivering it.
How big is it?
It will hold up to 63,000 spectators after the Games and up to 70,000 for concerts.
Is the park still open?
Some of the park is still open, and the government says more closures will be needed as construction goes on.
Sources: Queensland Government statements of 5 January 2026, 1 June 2026, 17 July 2026 and 18 November 2026. Last checked 21 November 2026.